Estimate total
$11,992.20
EST-208 from Your Contracting Co. for Acme Corporation, priced on $9,994 of cost and valid until Oct 14, 2026
- Price before tax
- $11,992.20
- Total cost
- $9,993.50
- Gross profit
- $1,998.70
- Deposit requested
- $3,597.66
How the price is built
| Step | Amount | Share of price |
|---|
| Materials and items | $4,300.00 | 35.9% |
| Labour (48 hours at $75.00) | $3,600.00 | 30% |
| Direct cost | $7,900.00 | 65.9% |
| Contingency (10%) | $790.00 | |
| Overhead recovery (15%) | $1,303.50 | |
| Everything the job costs | $9,993.50 | 83.3% |
| Profit markup (20%) | $1,998.70 | 16.7% |
| Price before tax | $11,992.20 | |
| Estimate total | $11,992.20 | |
The markup is 20% of cost but only a 16.7% margin on the price. Break-even on this job is $9,993.50, so anything below that price loses money.
This estimate holds for 30 days, until Oct 14, 2026. At a 16.7% margin, a $790 contingency that gets spent on surprises takes the profit down to 10.1% - which is why contingency belongs in the price rather than in the profit.